document_id: KC-PRO-GOV-001
|
|
title: Policy Review and Retirement Procedure
|
|
document_type: Procedure
|
|
domain: Governance
|
|
version: 1.0
|
|
status: Active
|
|
owner: Business Owner
|
|
reviewers:
|
|
- Operations Staff
|
|
approver: Business Owner
|
|
effective_date: 2026-04-03
|
|
next_review_date: 2027-04-03
|
|
supersedes: None
|
|
related_documents:
|
|
- KC-POL-GOV-001
|
|
related_systems:
|
|
- Policy Repository
|
|
- Forgejo Git
|
|
- Compliance Evidence Repository
|
|
retention_period: 3 years
|
|
confidentiality: Internal
|
|
---
|
|
|
|
# Purpose
|
|
|
|
This procedure defines the steps used to review active controlled documents and to retire documents that are superseded, obsolete, or no longer applicable.
|
|
|
|
# Scope
|
|
|
|
This procedure applies to all controlled documents maintained under the Kell Creations policy repository structure.
|
|
|
|
# Preconditions
|
|
|
|
Before starting this procedure, the following should exist:
|
|
|
|
- the target document is identified
|
|
- the current version is available in the repository
|
|
- the owner and approver are known
|
|
- supporting review or retirement rationale is available
|
|
|
|
# Procedure Steps
|
|
|
|
## A. Periodic Review Process
|
|
|
|
### 1. Identify review candidate
|
|
|
|
Identify a document for review using one or more of the following:
|
|
|
|
- scheduled review date
|
|
- business process change
|
|
- system change
|
|
- regulatory or governance update
|
|
- issue discovered during operations
|
|
- owner-requested review
|
|
|
|
### 2. Confirm current document state
|
|
|
|
Verify:
|
|
|
|
- document ID
|
|
- version
|
|
- current status
|
|
- owner
|
|
- file location
|
|
- related documents
|
|
- next review date
|
|
|
|
### 3. Evaluate the document
|
|
|
|
Review the document for:
|
|
|
|
- continued applicability
|
|
- accuracy
|
|
- clarity
|
|
- completeness
|
|
- consistency with current business practice
|
|
- consistency with related architecture, systems, and workflows
|
|
|
|
### 4. Determine review outcome
|
|
|
|
Select one of the following outcomes:
|
|
|
|
- no change required
|
|
- revise and resubmit
|
|
- supersede with a new version
|
|
- retire document
|
|
|
|
### 5. Record review result
|
|
|
|
Update the appropriate records, including:
|
|
|
|
- `review-calendar.csv`
|
|
- `document-control-log.csv`
|
|
|
|
If no change is required, update the next review date and close the review cycle.
|
|
|
|
## B. Revision and Supersession Process
|
|
|
|
### 6. Create revised draft
|
|
|
|
If revision is required, create or update the next version in the appropriate `drafts/` area.
|
|
|
|
### 7. Route for review
|
|
|
|
Move or track the revised document through the `review/` state and gather reviewer input.
|
|
|
|
### 8. Obtain approval
|
|
|
|
Obtain formal approval from the named approver.
|
|
|
|
### 9. Publish revised version
|
|
|
|
After approval:
|
|
|
|
- place the approved document in the correct `active/` location
|
|
- update version and effective date
|
|
- update the document register
|
|
- log the transition in the control log
|
|
|
|
### 10. Retire superseded version
|
|
|
|
Move the superseded active version to the appropriate `retired/` location and record the supersession in the control log.
|
|
|
|
## C. Retirement Process
|
|
|
|
### 11. Identify retirement basis
|
|
|
|
A document may be retired because it is:
|
|
|
|
- replaced by a newer version
|
|
- no longer applicable
|
|
- obsolete due to process or system change
|
|
- withdrawn by management decision
|
|
|
|
### 12. Confirm retirement impact
|
|
|
|
Before retiring the document, confirm:
|
|
|
|
- no current dependency requires it to remain active
|
|
- users can be directed to a replacement, if applicable
|
|
- related records are updated
|
|
- evidence of the retirement decision is captured when needed
|
|
|
|
### 13. Obtain retirement approval
|
|
|
|
The named approver must approve retirement before the document is removed from the active set.
|
|
|
|
### 14. Move document to retired state
|
|
|
|
Move the document to the matching path under `retired/`.
|
|
|
|
Do not delete retired controlled documents unless a separate retention rule explicitly authorizes deletion.
|
|
|
|
### 15. Update records
|
|
|
|
Update:
|
|
|
|
- `policy-register.csv`
|
|
- `document-control-log.csv`
|
|
- `review-calendar.csv` as applicable
|
|
|
|
### 16. Preserve evidence
|
|
|
|
Store supporting evidence in the appropriate evidence folder when required, including:
|
|
|
|
- approval note
|
|
- review outcome
|
|
- supersession reference
|
|
- retirement rationale
|
|
|
|
# Outputs
|
|
|
|
This procedure should result in one or more of the following:
|
|
|
|
- updated active document
|
|
- retired document
|
|
- updated review date
|
|
- updated registers and control log
|
|
- retained approval or retirement evidence
|
|
|
|
# Exceptions and Escalation
|
|
|
|
If review cannot be completed on time, or if ownership, applicability, or replacement status is unclear, escalate to the Business Owner.
|
|
|
|
If an active document appears unsafe, misleading, or materially outdated, it should be flagged for immediate review and may be temporarily withheld from operational use pending decision.
|
|
|
|
# Review and Revision History
|
|
|
|
| Version | Date | Description | Author | Approver |
|
|
|---|---|---|---|---|
|
|
| 1.0 | 2026-04-03 | Initial active release | Business Owner | Business Owner | |